   Q:消防工程施工步骤(zhou)

   A:一(yi)、 施工前准(zhun)备成立(li)项(xiang)目组
          1、项目部了解工程(cheng)概况(kuang)、图纸会审(shen),审(shen)定(ding)最佳施工方案(an),依据土建(jian)大计划确定(ding)我方工期、进度计划及(ji)用工计划;
          2、制定材(cai)料计划(hua),依据工程进(jin)度及施(shi)工图纸(zhi),合理(li)提供现场实际用量计划(hua),抄送采购(gou)部;
          3、项目(mu)主管接触建(jian)设(she)及(ji)监理单位办理一切开工手续(xu)(递交资质、组织设(she)计(ji)、开工报告等);
          4、组织施(shi)工人员进场,进行(xing)安全教(jiao)育(yu)及技术交底。


      二、施工工艺流程
       1、质安(an)部全程检(jian)查
     (1)、消防水系统
       组织项(xiang)目成员→熟悉图纸→施(shi)工(gong)(gong)(gong)资质、组织设计(ji)、开(kai)工(gong)(gong)(gong)报告,进(jin)场安全(quan)教育、技(ji)术交底、编(bian)制计(ji)划→钢管(guan)(guan)进(jin)场报验(yan)(yan)(yan)(yan)→预留孔洞尺寸核查→支吊架制作安装(zhuang)(zhuang)→管(guan)(guan)道除锈刷(shua)油(you)→主(zhu)管(guan)(guan)道安装(zhuang)(zhuang)→钢管(guan)(guan)检验(yan)(yan)(yan)(yan)批、隐(yin)蔽工(gong)(gong)(gong)程(cheng)报验(yan)(yan)(yan)(yan)→支、配管(guan)(guan)安装(zhuang)(zhuang)→阀(fa)门(men)、消(xiao)火(huo)栓(shuan)(shuan)进(jin)场报验(yan)(yan)(yan)(yan)及阀(fa)门(men)强度严密性试(shi)验(yan)(yan)(yan)(yan)→阀(fa)门(men)、消(xiao)火(huo)栓(shuan)(shuan)安装(zhuang)(zhuang)→阀(fa)门(men)、消(xiao)火(huo)栓(shuan)(shuan)检验(yan)(yan)(yan)(yan)批报验(yan)(yan)(yan)(yan)→喷头进(jin)场报验(yan)(yan)(yan)(yan)→喷头安装(zhuang)(zhuang)→稳(wen)压装(zhuang)(zhuang)置(zhi)、水(shui)(shui)泵(beng)、水(shui)(shui)泵(beng)接合(he)(he)(he)器进(jin)场报验(yan)(yan)(yan)(yan)→稳(wen)压装(zhuang)(zhuang)置(zhi)、水(shui)(shui)泵(beng)及水(shui)(shui)泵(beng)接合(he)(he)(he)器安装(zhuang)(zhuang)→水(shui)(shui)泵(beng)接合(he)(he)(he)器检验(yan)(yan)(yan)(yan)批报验(yan)(yan)(yan)(yan)→系统调试(shi)→管(guan)(guan)道强度严密性试(shi)验(yan)(yan)(yan)(yan)、管(guan)(guan)道清洗消(xiao)毒记(ji)录、消(xiao)火(huo)栓(shuan)(shuan)试(shi)射记(ji)录、管(guan)(guan)道通水(shui)(shui)试(shi)验(yan)(yan)(yan)(yan)报验(yan)(yan)(yan)(yan)→分(fen)部(bu)(子分(fen)部(bu))工(gong)(gong)(gong)程(cheng)报验(yan)(yan)(yan)(yan)→分(fen)项(xiang)工(gong)(gong)(gong)程(cheng)报验(yan)(yan)(yan)(yan)→水(shui)(shui)泵(beng)联(lian)动调试(shi)→竣工(gong)(gong)(gong)图制作→工(gong)(gong)(gong)程(cheng)自检→整改→自检合(he)(he)(he)格→报验(yan)(yan)(yan)(yan)→检测(ce)公(gong)司检测(ce)合(he)(he)(he)格→报验(yan)(yan)(yan)(yan)→消(xiao)防(fang)部(bu)门(men)验(yan)(yan)(yan)(yan)收(shou)合(he)(he)(he)格→工(gong)(gong)(gong)程(cheng)移交→售后服务
       (2)、火灾(zai)自动报(bao)警系(xi)统
        组(zu)织项目成员→熟悉图纸(zhi)→施工资(zi)质(zhi)、组(zu)织设计(ji)、开工报(bao)(bao)告,进场安全教(jiao)育、技术(shu)交底、编(bian)制(zhi)计(ji)划(hua)→钢(gang)管(guan)(guan)、桥架(jia)进场报(bao)(bao)验(yan)→钢(gang)管(guan)(guan)敷设(明敷钢(gang)管(guan)(guan)防火处(chu)理(li))→钢(gang)管(guan)(guan)、桥架(jia)检验(yan)批、隐蔽及分(fen)(fen)项工程报(bao)(bao)验(yan)→穿(chuan)引丝→桥架(jia)安装(zhuang)及桥架(jia)内布线(xian)(xian)→线(xian)(xian)缆(lan)进场报(bao)(bao)验(yan)→管(guan)(guan)内穿(chuan)线(xian)(xian)→接线(xian)(xian)(焊锡(xi))→管(guan)(guan)内穿(chuan)线(xian)(xian)检验(yan)批及分(fen)(fen)项工程报(bao)(bao)验(yan)→线(xian)(xian)路绝缘(yuan)测试→绝缘(yuan)电阻测试记录(lu)报(bao)(bao)验(yan)→设(she)备(bei)进场报(bao)验(yan)→设(she)备(bei)底座安(an)(an)装→设(she)备(bei)安(an)(an)装→设(she)备(bei)安(an)(an)装检(jian)(jian)验(yan)批及分项(xiang)(xiang)、分部/子(zi)分部工(gong)程(cheng)报(bao)验(yan)→系统调(diao)试→系统调(diao)试分项(xiang)(xiang)工(gong)程(cheng)报(bao)验(yan)→点位布置图制(zhi)作→工(gong)程(cheng)自检(jian)(jian)→整改→自检(jian)(jian)合格→报(bao)验(yan)→检(jian)(jian)测(ce)公(gong)司检(jian)(jian)测(ce)合格→报(bao)验(yan)→消(xiao)防部门验(yan)收合格→工(gong)程(cheng)移交→售后服务


      三、 工程部自检 
      1、消(xiao)防(fang)(fang)水系统(tong) 检(jian)测依据:DB64/T404-410-2005《消(xiao)防(fang)(fang)系统(tong)质量检(jian)验(yan)评定(ding)规(gui)程》、GB50261-96《自动喷水灭火(huo)系统(tong)施工及(ji)验(yan)收规(gui)范》 检(jian)测项目(mu):消(xiao)防(fang)(fang)水泵、水泵接合器(qi)(qi)、室外(wai)消(xiao)火(huo)栓、输(shu)水管网、压力(li)、主要设备、消(xiao)防(fang)(fang)水池、消(xiao)防(fang)(fang)水箱、气压给水装置、报警(jing)阀(fa)组(zu)、水力(li)警(jing)铃、水流指(zhi)示器(qi)(qi)、喷头、系统(tong)联动试验(yan)
       2、火(huo)灾(zai)(zai)(zai)自动(dong)报(bao)警系统(tong)(tong) 检(jian)测(ce)依据:DB64/T404-410-2005《消防系统(tong)(tong)质量检(jian)验(yan)评定规(gui)程》、GB50166-98《火(huo)灾(zai)(zai)(zai)自动(dong)报(bao)警系统(tong)(tong)施工及验(yan)收规(gui)范》 检(jian)测(ce)项目:配管、系统(tong)(tong)布线(xian)、探测(ce)器的安装、手动(dong)报(bao)警按钮、火(huo)灾(zai)(zai)(zai)报(bao)警控(kong)(kong)制器、楼(lou)层显示器、消防控(kong)(kong)制室、系统(tong)(tong)联动(dong)试验(yan)以上(shang)两项需自检(jian)合格。


     四、 申报检验

      1、 检测公司(si)检测 2、 检测合格(ge) 3、 申报消(xiao)防部门(men)验收 4、 验收合格(ge)


     五(wu)、 验收(shou)合格

     1、 对用(yong)户进行(xing)系统(tong)操作(zuo)培训(xun)受训(xun)人员签字确认 2、 移交相关工(gong)程资料,准(zhun)备(bei)决算资料,配合财务部做好工(gong)程款回收(shou)工(gong)作(zuo) 3、 建立工(gong)程售后服(fu)务档(dang)案对用(yong)户进行(xing)跟踪服(fu)务。

Q:消防工程主要施工内容

A:火(huo)灾(zai)自动报(bao)警及(ji)联动系(xi)统(tong),消防给水及(ji)室(shi)内(nei)外消火(huo)栓系(xi)统(tong),自动喷水灭火(huo)系(xi)统(tong),气体(ti)灭火(huo)系(xi)统(tong),防排(pai)烟机通风空调(diao)系(xi)统(tong),防火(huo)卷帘、挡(dang)烟垂壁和防火(huo)门(men)。
以下为消(xiao)防安装工(gong)程必要的施(shi)工(gong)流程。
       1、安装准(zhun)备及材料要求
      (1)消(xiao)防工(gong)程施工(gong)前,必须协助甲方(fang)进行消(xiao)防设施的设计审(shen)(shen)核,未(wei)经设计审(shen)(shen)核或设计审(shen)(shen)核 不合格(ge)不得擅自施工(gong)。
      (2)消(xiao)防工(gong)程施工(gong)前(qian)必须向消(xiao)防部门申报有(you)关(guan)资(zi)料(liao),办(ban)理消(xiao)防施工(gong)进场(chang)许可证(zheng)。
      (3)所选(xuan)用的材料(liao)必须在消防部门经过登记并(bing)具有(you)消防部门发(fa)放的准(zhun)销证。
      2、消(xiao)防(fang)工(gong)程(cheng)施工(gong)阶段(duan)
      喷(pen)头安装、报警阀组(zu)安装、消火栓箱(xiang)安装等其它组(zu)件安装
      3.、消防系(xi)统调试及验收(shou)